Skip to main contentSkip to main navigationSkip to footer content

Massasoit’s Transformation Through Renovation Project is a $52 million capital project that will bring state-of-the-art classrooms and labs to the College’s Brockton campus. The multi-year project, which began in July 2022, includes the gut-rehab of two instructional buildings to create a new Science building and a new Health Sciences building. The new spaces – designed with input from students, faculty, and staff – will impact thousands of students across nearly all of Massasoit’s academic divisions, and will enhance how the College trains our community’s future professionals.


Project Updates


Steering Committee – Policy & Decision Making

President Bill Mitchell; Vice President Margaret Gazzara Hess; Vice President Bill O'Neill; Interim Vice President Rita Jones-Hyde

Programming Team

To define in detail space requirements to meet current & future programmatic needs.
David Auperin; Michael Bankson; Susan Clover; Kevin Doten; Ana Estabrooks; Rachel Franciosi; Richard Hadley; William Hanna; Eve Jankey; David Johanson; Denise Logan; Marie McDonnell; Melany McFadden; Bill O’Neill; Catherine Powers-Ozyurt; Andrew Oguma; Jennifer Pike; Katie Ruggieri; Jesse Schreier; Amee Synnott; Andrea Torres; Kendra Twomey

Logistics Team

To identify and recommend swing space and the construction process.
Angelina Avedano; Paul Chiano; Richard Hadley; Jen Holbrook; Rita Jones-Hyde; Jeffrey Mei; Michael Mezzano; Bill Morrison; Bill O'Neill; Kim Sylvia; Christofer Volz

Information Technology Team

To provide project teams with technical expertise related to Information Technology.
Jackie Barrett; Patrick Mauretti; Bill Morrison

Communications Team

To provide periodic updates to the college community on the status of the project.
Jen Holbrook; Amity Kelley; Lloyd King; Bill Morrison; Alex Villanueva; Karina Sallaway

Advancement Team

To build a capital campaign to support the philanthropic source of funding.
President Mitchell; Margaret Downey; Alex Villanueva

Project Tasks Dates Approximate Months
Project Prep/Scope Confirmation July 2022 - August 2022 2 - Completed
Select Architectural Firm (DSB) September 2022 - November 2022 3 - Completed
Study, Schematic Design December 2022 - December 2023 12 - Completed
DCAMM Certification of Study December 2023 1 - Completed
Detailed Design/Construction Documents January 2024 - March 2025 15 - Completed
Bidding/Permitting March 2025 - May 2025 3 - Completed
Construction - Liberal Arts to New Science Renovation May 2025 - July 2026 15 - In Process
Construction - Science to New Nursing & Allied Health July 2026 - July 2027 12
  Approx. Total Months 63

April 13, 2022 - Massasoit Community College announced as a recipient by Governor Baker in the latest round of Higher Education Capital Grants.

June 28, 2022 - President DiPasquale charges Project Teams that will work collaboratively with faculty and staff on key capacities.

August 3, 2022 - Designer Selection Board chooses Jones Architecture for architectural & engineering services.

October 25, 2022 - Start-Up Workshop held with DCAMM, Jones Architecture/Studio Luz, Design Consultants, Massasoit Project Teams

November 7, 2022 - Project Planning Meetings (Review of 2019 Readiness Report and Inclusive Design)

November 14, 2022 - Science, Math, Nursing, and Allied Health Programming Meetings and Building Walkthroughs (#1)

December 7 & 9, 2022 - Science, Math, Nursing, and Allied Health Programming Meetings (#2)

January 17 & 18, 2023 - Faculty and Staff Local College Site Visits for Recently Renovated Science, Nursing, & Allied Health Spaces

January 24, 2023 - Science, Math, Nursing, and Allied Health Programming Meetings (#3)

March 8 & 9, 2023 - Campus Community Engagement Session #1 & Project Update for Massasoit Project Teams presented by DCAMM, Jones Architecture/Studio Luz, Design Consultants

March 30, 2023 - Respiratory, Science & Math Programming Meeting (#4)

April 18 & 27, 2023 - Nursing Programming Meetings (#4)

June 14, 2023 - Existing Furniture & Systems Walkthrough with Design Team, DCAMM, BVH, Science, Nursing, and Allied Health Faculty and Staff

August 21, 2023 - Schematic Design Kickoff Meeting with all Project Teams (Dining Hall)

October 16, 2023 - Universal Design Workshop #1 (SD)

November 3, 2023 - Universal Design Workshop #2 & Interior Experience Meeting #1 (SD)

November 14, 2023 - Campus Community Engagement Session #2 for Massasoit Project Teams and Campus Community presented by DCAMM, Jones Architecture/Studio Luz, Design Consultants

December 15. 2023 - Interior Experience Committee Meeting #2 (SD)

August 6, 2024 - *Building Experience Committee Meeting #1 (DD)

*(newly combined Committee from Interior Experience & Universal Design) 

August 6, 2024 - Science, Nursing, Allied Health Meeting (DD)

September 16, 2024 - Building Experience Committee Meeting #2 (DD)

October 18, 2024 - Building Experience Committee Meeting #3 (DD)

November 2, 2024 - Open House Poster Display

December 5, 2024 - Student Senate Engagement Workshop

July 16, 2025 - Science Building Groundbreaking


(SD) = Schematic Design Phase

(DD) = Detail Design Phase